The Mall at Green Hills

Location: Ann Arbor, Michigan
Pinnacle created the 3D BIM Model of The Mall at Green Hills (4 floors, 1 zone) for The Whiting-Turner Contracting Company at LOD 300. The purpose of construction was to use the models for 3D coordination, clash mitigation and visualization. The BIM models of The Mall at Green Hills were divided into separate levels and zones for efficient working and coordination of various trades by focussing on particular building location. Moreover, the breakups helped to reduce the file size in order to smoothly handle and deliver the files avoiding technical glitches.

Key Project Details

Architect:Omniplan
Contractor(s):The Whiting-Turner Contracting Company
Owner:The Taubman Company

Value Added

We raised 16+ RFIs for Architecture & Structure and 16 RFIs for MEP trades pertaining to missing ceiling dimension, steel column & framing location dimension, location dimension from grid reference, kicker brace detail, member specification, slab thickness, sheet reference, footing layout mismatch between plan and details and more.

We generated coordinated models using BIM and allowed our client to check possible interference among all building systems. Our 3D BIM Models helped to detect clashes for eliminating major system conflicts before installation.

Key Project Details

Architect:Omniplan
Engineer:E&S Construction Engineers
Contractor(s):The Whiting-Turner Contracting Company
Owner:The Taubman Company

We'd love to hear about your next project.