Location Rapid City, South Dakota, USA

Year November, 2020 - March, 2021

Key Project Details
share link

Project Area:2,15,080 sq.ft.

view Full Key Project Details
close arrow
Key Project Details
share link

Project Area:2,15,080 sq.ft.

Architect:Childers Architect

Engineer:EAPC - 6 Engineers

Contractor(S):Tessier’s Inc (Mechanical)

Owner:NA

Trades Covered:MEP Contractors

LOD:400

Software:AutoCAD MEP Fabrication 2018, Navisworks

Verticals:  MEP Engineering

Download Project Details
Rapid-City-Health-Center
Multi-level BIM 3D coordination model for a healthcare facility
BIM coordination model showing integrated MEP systems
3D MEP coordination and clash-detection model
3D architectural rendering of a multi-wing healthcare building

The Rapid City Health Center is a multi-phase design-build healthcare facility in Rapid City, South Dakota. Pinnacle delivered Healthcare BIM Services in South Dakota for the 215,080 sq. ft. facility.

The building includes a basement, Levels 1–3, and a roof. It features operating theaters, OPD areas, triage rooms, ultrasound rooms, laboratories, and other healthcare spaces.

Pinnacle’s scope covered MEP 3D modeling, coordination, and 2D drawings. The team also supported clash resolution, client-specific documentation, and fabrication-ready sheet metal drawings.

MEP BIM Modeling Services in South Dakota

Pinnacle developed 3D MEP models and 2D drawings for the healthcare facility. The team coordinated MEP services with other trades and adapted the models to client requirements.

The scope included:

  • • 3D MEP modeling
  • • Multidisciplinary coordination
  • • 2D drawing preparation
  • • Clash resolution
  • • Shop drawing preparation
  • • Client-specific documentation

MEP BIM Coordination Services in South Dakota

The project involved a large healthcare facility, multiple trades, and continuous model changes. Pinnacle coordinated the services through regular coordination meetings and shared project files.

The team identified and raised issues related to missing data, conflicting information, accessibility, and constructability. Pinnacle also worked with subcontractors to establish new zones for service routing.

This zoning approach provided sufficient space for different services and improved coordination between trades.

Key Project Details

Project Area:2,15,080 sq.ft.

Architect:Childers Architect

Engineer:EAPC - 6 Engineers

Contractor(s):Tessier’s Inc (Mechanical)

Owner:NA

LOD:400

Trades Covered:MEP Contractors

Software:AutoCAD MEP Fabrication 2018, Navisworks

Verticals:  MEP Engineering

Download Project Details

Challenges & Solutions

Conflicting Input Data: The IFC contained data conflicts when compared with related project documents and standards.

Solution: Pinnacle raised the conflicts with the client and suggested potential solutions. The client then raised an RFI with the engineers and obtained a revised IFC.

Large Project Area and Limited Timeline: The 215,080 sq. ft. facility required extensive modeling within a limited timeframe.

Solution: Pinnacle allocated additional resources and optimized its workflow to complete modeling and coordination within the required schedule.

Coordination Across Multiple Trades: The project required regular coordination meetings with other trades, including meetings outside standard working hours.

Solution: Pinnacle aligned its schedule with the project's coordination requirements and attended regular meetings to streamline coordination.

Continuous Model Changes: Frequent model changes made it difficult to resolve issues and coordinate services within defined areas.

Solution: Pinnacle coordinated all trades during the initial coordination stage and maintained files in a shared folder. The subcontractors then established new service zones to provide sufficient routing space.

Client-Specific Standards: The client required specific shop drawing formats and detailed information for fabrication and installation.

Solution: Pinnacle followed the client's standards and provided system-specific drawings with dimensions, elevations, tags, lengths, item numbers, and required sections.

Value Delivered Through MEP BIM Coordination

Pinnacle's coordinated MEP approach delivered:

  • 75+ issues raised with 3D snapshots during coordination meetings.
  • 450+ clashes resolved, including 100+ critical clashes.
  • Improved modeling efficiency using MEP CAD Fabrication.
  • Clear routing direction for pipes, cable trays, and fire protection systems to maintain adequate clearances.

Outcomes

Multi-level BIM 3D coordination model for a healthcare facility

BIM coordination model showing integrated MEP systems

3D MEP coordination and clash-detection model

3D architectural rendering of a multi-wing healthcare building