Location Washington, DC, USA
Year October 2017 - February 2018
Project Area:10,000 sq. ft.
Architect:Omniplan
Engineer:8 Engineers
Contractor(S):Shapiro & Duncan, Inc.
Owner:NA
Trades Covered:Architecture, Structure, Plumbing, Mechanical Piping
LOD:300
Software:Revit 2017, Navisworks 2017, Autodesk ReCap 360, Newforma
Verticals: 3D Model Creation
The G30 Project comprised Phase I and II Boiler and Chiller Plant Rooms, each located on a single level in Washington, D.C., USA. Following detailed laser scanning by Shapiro & Duncan for the renovation works, Pinnacle utilized RCS and RCP scan files to develop Architectural, Structural, Mechanical, and Plumbing 3D models.
Using its Scan to BIM Services, Pinnacle converted the captured scan data into coordinated models, completing detailed service modeling for both boiler and chiller room phases. This work supported the renovation and expansion planning of the existing facility.
The scope of work included:
Point Cloud to BIM Conversion played a critical role in supporting the renovation of the existing facility. Pinnacle developed coordinated 3D models across all disciplines by accurately modeling the required elements from the scan data.
The project involved MEP Scan-to-BIM Modeling alongside architectural and structural modeling to create detailed representations of existing building elements and services. This approach helped maintain model accuracy and improve interdisciplinary coordination.
Contractor(s):Shapiro & Duncan, Inc.
Challenge: Scan data was unavailable in certain areas, resulting in inconsistencies in the project inputs.
Solution: Pinnacle modeled the missing elements using documented assumptions. The team also tracked these assumptions through an assumption log with corresponding element IDs.
Challenge: Wall locations were not clearly visible due to obstructions from tanks and equipment.
Solution: The team modeled wall alignments using the nearest visible references in the scan data.
Challenge: The concrete pad beneath the boiler equipment was not clearly identifiable in the scan.
Solution: Pinnacle assumed a width of 1 foot for the pad while maintaining less than 1-inch deviation between the model and scan data.
Pinnacle delivered several benefits through its modeling and coordination expertise: