Haydon Gardens – The Minories

Location London, United Kingdom

Year April 2022

Key Project Details
share link

Project Area:77070 sq ft.

view Full Key Project Details
close arrow
Key Project Details
share link

Project Area:77070 sq ft.

Architect:ACME

Engineer:

Contractor(S):Regal Four London Construction Ltd

Owner:Gloster MEP Limited

Trades Covered:Mechanical, Plumbing, Electrical

LOD:400

Software:Revit 2021

Verticals:  BIM Powered MEP Engineering Services

Haydon Gardens – The Minories | BIM Powered MEP Projects image 1
Haydon Gardens – The Minories | BIM Powered MEP Projects image 2

The Minories site project Haydon Gardens is primarily a residential tower that is spread over a 77070 sq. ft. area. Consisting of 87 residential apartments with 3 floors of penthouses, it is a unique contemporary landmark site in the vicinity that brings nature and architecture together to reveal a great construction marvel. Visually striking, yet sensitively stitched into its urban context, Haydon Gardens offers breathtaking views and the best of London, right on its doorstep.

Key Project Details

Project Area:77070 sq ft.

Architect:ACME

Engineer:

Contractor(s):Regal Four London Construction Ltd

Owner:Gloster MEP Limited

LOD:400

Trades Covered:Mechanical, Plumbing, Electrical

Software:Revit 2021

Verticals:  BIM Powered MEP Engineering Services

Scope of Work

 
  • 3D modeling of the MEP items
  • Coordination of all services
  • Shop Drawing Preparation
  • BWIC Drawing Creation
  • Utility Cupboard Drawing Creation

 

Challenges and Solutions

 

  • The main challenge for this project was the coordination of services due to the complex design of the building. Due to the matchbox-shaped architecture of the building, MEP riser fixing was a huge challenge.

 

After several design iterations and a series of cross-channel discussions, the challenge was evaded and fixed.

 

  • Due to the complex architectural design, there were many changes and updates done to the architectural model. This took more time than usual as it was difficult to track the changes and analyze the impact on MEP due to its design complexities.

 

To overcome this we used the BIM 360 tool to identify the changes required and updated the MEP services accordingly.

 

Pinnacle’s Value Addition

 

Pinnacle worked on some of the most crucial clashes in the process. We raised 41 RFIs, regarding missing and conflicting data, conductibility issues, and maintenance or accessibility issues. We solved 200 critical disputes in the process.

 