UK Medical Center

Location Lexington, KY

Year 2022

Key Project Details
share link

Project Area:11,240 sq. ft

view Full Key Project Details
close arrow
Key Project Details
share link

Project Area:11,240 sq. ft

Architect:NA

Engineer:NA

Contractor(S):Stengel Hill Architecture

Owner:University Of Kentucky

Trades Covered:2D/3D Drawings

LOD:400

Software:Revit, Fabrication 2022

Verticals:  Mechanical and Plumbing Contractors

UK Medical Center- Pavillion H-Behavioral

Pinnacle Infotech executed the University of Kentucky HealthCare Medical Center project in Lexington, Kentucky. Pinnacle’s scope of work for the project included 2D/3D drawings of the 11,240 Sq Ft structure encompassing a large setup of hospitals, clinics, outreach locations, patient care services, and UK health profession colleges on the premises. Pinnacle Infotech coordinated with the sub-contractors CINFAB LLC, for Ducting Scope and Thomas J. Dyer Company for Mechanical Pipe and Plumbing Scope to cohesively accomplish project requirements across production timelines. 

Key Project Details

Project Area:11,240 sq. ft

Architect:NA

Engineer:NA

Contractor(s):Stengel Hill Architecture

Owner:University Of Kentucky

LOD:400

Trades Covered:2D/3D Drawings

Software:Revit, Fabrication 2022

Verticals:  Mechanical and Plumbing Contractors

Scope of Work:

Pinnacle’s team received a design contract for Sheet Metal and Mechanical Piping & Plumbing for the UK Medical Center project and was asked to offer MEP BIM Services and to develop 2D drawings to be used for coordination review with other services. 

Challenges & Solutions:

Challenges:

The UK Medical Center Lexington KY was a conventionally designed structure, doing renovation of which was a challenging task.

As it was a renovation job for a conventional building structure, it became challenging to identify the exact connection points for new services against the existing work and consequently figure out and model the points at a certain elevation.

Solution:

Point coordination and space management for the UK Medical Center Lexington project was done, going with a hyper-integrated BIM implementation process. We considered a fly zone for our services and tried to leave space margins as much as possible for other services and used a ‘point cloud’ for existing points of connection and coordination. In some places, we re-sized the ducts and demolished existing elements as per the site condition.

Pinnacle’s Value Addition:

The team at Pinnacle worked on appointing spatial coherence by producing process-critical 2D/3D drawings following all the architectural standards and conventions best responding to the project requirements. Our expert MEP BIM Modeling Services precisely laid the restructuring plan for the building which led to the successful completion of the overhauling project.

Outcomes:

1. Ducting Installation Drawings

Ducting Installation Drawings - UK Medical Center

 

2. Ducting Shop Drawings

Ducting Shop Drawings - UK Medical Center

next-arrow Previous Project

The University of Arizona Applied Research Building

View Next Project next-arrow