Edwards Vacuum Phase II

Location Hillsboro, OR

Year 2022

Key Project Details
share link

Project Area:35,000 sq. ft.

view Full Key Project Details
close arrow
Key Project Details
share link

Project Area:35,000 sq. ft.

Architect:NA

Engineer:NA

Contractor(S):NA

Owner:Whitaker Ellis Builders, Inc.

Trades Covered:Concrete

LOD:400

Software:Revit 2021

Verticals:  Concrete Contractors

Edwards Vacuum Phase 2

The Project “Edwards Vacuum Phase II” is a Commercial Building at 6225 NE Century Blvd., Hillsboro, OR 97123. The building has two floors with roof. The total area of the project is approx. 35,000 sq. ft. The Edwards Vacuum Hillsboro project required the concrete drawings and models to be created for a 35,000 sq. ft. area using Revit 2021 software. 

Key Project Details

Project Area:35,000 sq. ft.

Architect:NA

Engineer:NA

Contractor(s):NA

Owner:Whitaker Ellis Builders, Inc.

LOD:400

Trades Covered:Concrete

Software:Revit 2021

Verticals:  Concrete Contractors

Scope of Work:

Concrete 3D Model: Our BIM modeling services delivered concrete 3D models of footings, retaining wall/structural wall, concrete tilt panels (20), slab-on-grade, concrete curbs, thickened slab, metal deck, and embeds.

Concrete 2D Drawings: With our expertise in BIM for Concrete Contractors we created precise foundation drawings, slab-on-grade drawings, sawcut drawings, panel elevation drawings, metal deck drawings, and section and details.

Challenges & Solutions:

Challenges:

There were no embed submittals when the planning was done so a lot had to be assumed. Also, there was a risk of manpower crisis and assumption on the estimate as well. The input drawings were like DD set and a drastic mismatch was found between structural and architectural drawing sets.

Solutions:

We initiated approximately 30 Request for Information (RFI) submissions addressing discrepancies in the drawings, a crucial step that enabled our client to pinpoint and rectify all necessary areas. Leveraging the expertise of trade professionals, we meticulously scrutinized the embedded drawings, guaranteeing a seamless project delivery within the designated time frame, effectively surmounting every obstacle encountered along the way.

Pinnacle’s Value Addition:

  • Our prompt delivery of the Edwards Vacuum company project drawings adhered strictly to the designated time frame, affording the client ample opportunity to meticulously review each detail and effectively document all necessary changes.
  • Pinnacle's astute assumptions and proactive identification of areas necessitating clarification expedited the entire construction process, ensuring smooth progress and timely completion.
  • Our provision of comprehensive concrete quantity take-off services facilitated the client's estimation process, offering invaluable insights into material requirements and aiding in budgetary planning.
Sections & Details:

Edwards Vacuum Phase 2 - Section and Details

 

Level-2 Metal Deck Section & Details

Edwards Vacuum Phase 2 - Metal Deck Section and Details

 

Tilt-Up Panel

Edwards Vacuum Phase 2 - Tilt Up Panel

 

Footing Embed Section & Detail

Edwards Vacuum Phase 2 - Footing Embed Section and Detail

Foundation Plan Part A

Edwards Vacuum Phase 2 - Foundation Plan Part A

 

3D View Of Foundation

Edwards Vacuum Phase 2 - Foundation Plan Part B

next-arrow Previous Project

Blake Apartments

View Next Project next-arrow

Alderman Library Renewal